wind

E.ON awards wind farm foundations contract to TAG Energy Solutions

E.ON and TAG Energy Solutions has awarded TAG Energy Solutions to manufacture 16 monopiles and transition pieces for E.ON’s Humber Gateway offshore wind farm.
E.ON awards wind farm foundations contract to TAG Energy Solutions

The contract will see the Teesside based manufacturing firm become the first UK manufacturer to secure a substantial monopile and transition piece project for a wind farm in British Waters. An additional 60 people will be employed to deliver the contract.

Preparation work for the manufacturing of the sixteen, 60 metre long, 650 tonne monopiles and associated transition pieces will begin immediately at TAG Energy Solutions’ state-of-the-art production facility on the banks of the River Tees.

The first steel is expected to arrive in March and the contract is planned to be completed by quarter four 2013.

E.ON’s £736 million Humber Gateway wind farm, situated 8km off the Yorkshire Coast close to the mouth of the Humber Estuary, will consist of a 73 turbine array that will generate up to 219 MW of electricity, enough energy to power up to 170,000 homes.

“Securing investment in clean energy that supports growth and jobs is an absolute priority," said Edward Davey, UK Secretary of State for Energy and Climate Change. "I want to congratulate TAG Energy Solutions on becoming the first UK manufacturer to secure a contract of this kind for a wind farm in British Waters. I hope that they are the first of many."

Davey continued, “The development of a thriving UK supply chain is vital to support our rapidly-growing offshore wind industry. The Government is working with industry so it can source at least half of the content for offshore wind projects from within the UK. This will help build the lasting legacy of a strong domestic offshore wind manufacturing capability.”

Alex Dawson, Chief Executive of TAG Energy Solutions, said, “This high profile contract represents a significant achievement in TAG Energy Solutions development and the important role it plays in the manufacturing of components for the offshore renewables sector. We are very pleased to be working with E.ON and this award demonstrates we have the skills, products and capabilities to serve the offshore wind industry.”

“We are in the unique position of being the first, fully prepared British manufacturer to provide volume monopiles and transition pieces for UK wind farm developments." he continued. "E.ON has demonstrated its confidence in TAG Energy Solutions and British manufacturing and we are very proud to be part of one of the country’s flagship wind farm developments.”

Construction on E.ON’s Humber Gateway is well underway, with first foundations expected this summer, and completion due in 2015.

For additional information:

Tag Energy Solutions

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).