Grid connection delays top barriers to battery storage rollout, say delegates at Battery Energy Storage conference

An overwhelming 98 percent of delegates at Tamarindo’s inaugural Investing in Battery Energy Storage conference in London identified grid connection delays as the biggest execution bottleneck affecting deployable capital.
Courtesy of US Bureau of Land Management.
Courtesy of US Bureau of Land Management.

Gathered in London for the conference, battery storage industry leaders agreed that grid connection delays are causing projects to stall, sometimes for years. This underlined mounting pressure on infrastructure as investment accelerates, with just 2 percent pointing to supply chain constraints.

This challenge is reflected at the project level, where more than three-quarters (78 percent) said grid connection queues are the regulatory barrier most responsible for delaying battery storage projects in markets across Europe. Other factors - including market access restrictions (11 percent), revenue stacking limitations (6 percent), and permitting timelines (4 percent) – were seen as significantly less impactful.

Despite these constraints, investment appetite remains strong, with over half (52 percent) of respondents identifying energy arbitrage as the primary revenue stream currently driving battery storage investment in Europe. Corporate power purchase agreements (PPAs) followed at 23 percent, while frequency response (13 percent) and capacity markets (12 percent) were seen as less dominant drivers.

The findings come at a time when the battery storage sector is scaling rapidly and requiring significantly greater levels of capital.

“Storage is no longer a niche financing theme; it’s now an active and fast-growing market with huge potential and scale” said Stephen Jennings, Chief Sustainability Officer, EMEA at MUFG. “Given the magnitude of expected capex needs in Europe in the coming years, the key question becomes how we can ensure these projects remain bankable and continue to attract the liquidity required to fund them.”

While investor appetite is certainly there, a series of structural barriers are holding the sector back, most notably securing a grid connection, which has become the single biggest bottleneck to project deployment, with queues stretching from months to years as projects compete for capacity.

“Right now, the energy storage market – and particularly the BESS market – has real momentum” added Adam Barber, Chief Executive Officer at Tamarindo. “In the space of just a few years, the industry has undergone an incredible transformation. It was great to be able to gather industry leaders to share their reflections and thoughts as to where the market is headed. The discussions highlighted how the sector is actively grappling with these challenges and exploring practical solutions to keep investment flowing and projects moving forward.”

For additional information:

Tamarindo

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).