ocean energy

Ocean Power Technologies completes testing of next generation power units

Ocean Power Technologies, Inc., a specialist in wave energy technology, announced the successful completion of extensive factory acceptance testing of next generation power take-off (PTO) units to be used with its utility-scale PowerBuoy.
Ocean Power Technologies completes testing of next generation power units

The PTO has now been shipped from the company’s facility in Pennington, New Jersey to Oregon Iron Works, where it will be integrated into the spar of the buoy in advance of deployment off the coast of Reedsport, Oregon.

During testing, the PTO was subjected to varying simulated wave conditions to measure overall functioning and reliability, and it performed as expected in each area studied.

The new direct drive system is a much larger version of that which was recently utilized in the Company’s PowerBuoy deployed off Oahu, Hawaii, for two years in a project with the US Navy.

It is expected to provide increased efficiency and reliability compared with the previous hydraulic-based PTO design used by OPT in earlier PowerBuoys.

“We are excited to see our next generation power take-off successfully complete extensive survival and operational mode testing. We are now working to integrate it into the spar of the PB150 with the help of Oregon Iron Works’ professional team,” said Charles F. Dunleavy, Chief Executive Officer of OPT.

“We expect the PowerBuoy to be ready for deployment off the coast of Reedsport, Oregon late this summer and look forward to an ocean demonstration that can pave the way for additional units in the region – with the eventual goal of a wave power station serving thousands of local residents and businesses,” he said.

Upon completion of integration, the spar will be transferred to Vigor Marine, a leading provider of shipbuilding, ship repair and other industrial services in Portland, Oregon, for the final buoy assembly and testing ahead of deployment.

The buoy will be launched using one of Vigor Marine’s floating drydocks, which will facilitate the handling and water launch of the PowerBuoy. Once in the water, the PowerBuoy will be towed from Portland to the Reedsport/Coos Bay area for interim staging prior to final deployment and installation.

The towing plan has been approved by the United States Coast Guard Marine Safety Office in Portland. The final stage will involve towing the PowerBuoy to the Reedsport ocean site, where it will be connected to the mooring system that will be deployed with the assistance of marine contractor Northwest Underwater Construction, as well as other local companies, including Knutston Towboat Company.

Subsequent to deployment, a period of commissioning will occur before full-scale power generation testing begins. During the course of the ocean operations, periodic inspections will be conducted using local marine operations personnel and vessels. OPT’s remote communications and operations control system will allow continuous monitoring of all aspects of the performance of the PowerBuoy.

For additional information:

Ocean Power Technologies

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).